Within period of time from 2000 until 2019 “Aspmk-519” Llp has completed more than 140 constructions, reconstructions and repairmen projects in power distribution industry. More than 6400 km of overhead power distribution lines has been constructed that consists from 2300 km of 110 kV, 2700 km of 220 kV and 1400 km of 500 kV. More than 110 substations has been reconstructed that consists from 50 pc of 110 kV, and 60 of 220 kV and 500 kV. More than 3400 km of optical cables has been installed that consists from more than 3100 km of OPGW and
310 km of underground optical cables.
New advanced technologies and materials are used at project implementation to ensure high quality and on-time completion of works:
Wire installation and ground conductor installation under tension
Use of fiber optic cables built in the ground conductors to install communication channels and for remote controlled operations
Design and manufacture of relay protection systems employing Siemens, ABB and Schneider Electric microprocessor technologies
Design, manufacture and setting of electric power control systems (SCADA)
Installation and testing of SF6-insulated equipment including 500kW equipment
Installation of 110kW cables with XLPE insulation.